Guides, Home

Get a new electricity connection, or change the name or load

I need a new electricity connection, or a change of name or load on my existing one. How do I apply, how long can the discom take, and what if it is late?

Your electricity distribution company (discom) must connect you, or change your connection, within fixed times once your application is complete: at most 3 days in metropolitan areas, 7 days in other municipal areas, 15 days in rural areas and 30 days in rural hilly areas. These caps come from the Electricity (Rights of Consumers) Rules 2020 as amended in 2024. The clock starts only when your application is complete and acknowledged, so keep the registration number.

7 steps, each waiting on an office or someone else, 6 legal deadlines, some rules differ by state. Checked against the law and official sources on 31 October 2026.

Open as a plan

Is this the right guide?

It is for you if

  • You need a new electricity connection for a home or other premises
  • You want to change the name on an existing connection, for example after buying the home or after the account holder’s death
  • You want to increase or reduce the sanctioned load, or change the category
  • Your discom has not connected you, or made the change, within the time limit

It is not for

  • Disputing a high or wrong electricity bill
  • Rooftop solar and net metering applications
  • Assessments for theft or unauthorised use of electricity

Before you start

5 documents
  • Find out which discom serves the premises, for example from a neighbour’s bill.
  • Decide the load you need in kW and the category, such as domestic or commercial.
  • Ask whether the premises are in a metropolitan, other municipal or rural area. This decides your time limit.
  • If you rent, use proof of occupancy such as your rent agreement; the Rules also allow another address proof if you have no ownership or occupancy proof.
  • For a change of name, check your discom’s published list of documents for changes.

Documents

0 of the 3 documents every applicant needs are ticked. Still to get: Identity proof of the applicant; Proof of ownership or occupancy of the premises; The load in kW and the category you need. Tick what you have; the ticks stay in this browser only.

  • every applicant

    For example a passport or Aadhaar card, as rule 4(9) gives as examples.

    Used at step 2

  • every applicant

    If you have neither, rule 4(9) allows any other address proof that you have not already given as identity proof.

    Used at step 2

  • every applicant

    For example domestic or commercial. The discom’s form asks for these.

    Used at step 2

  • only if it applies to you

    Only for a change of name, load or category on an existing connection.

    Used at step 2

  • only if it applies to you

    Your State Commission specifies the documents for changes to an existing connection, and your discom must publish the list.

    Used at step 2

Step by step

  1. Find your discom’s procedure and charges

    Your electricity distribution company (discom)

    Every discom must publish its procedure, the documents it needs and its charges on its website and on the notice board of its offices (rule 4(1)). Application forms must be free, and every discom must run a web portal and a mobile app for applications (rules 4(2) and 4(3)). Find the ‘new connection’ or ‘change of name’ service on your discom’s website or app.

    Fee
    Application form: free1

    Watch out

    • Check any amount you are asked to pay against the discom’s published charges.
  2. Apply and get a registration number

    Your discom’s portal, app or local office

    Apply online or at the office. For connections up to 10 kW, or a higher load if your State Commission allows, the discom may ask for only two documents: identity proof, and proof of ownership or occupancy of the premises (rule 4(9)). A complete application counts as received on the date the acknowledgement with a registration number is generated; for a paper application, that must happen within a time the Commission sets, not more than 24 hours (rule 4(7)). For a change of name or load, apply the same way; your State Commission sets the documents for changes.

    Time limit
    Acknowledgement of a paper application within the time the Commission sets, not more than 24 hours1Electricity (Rights of Consumers) Rules 2020, rule 4(7)
    Fee
    Connection charges are set by your State Electricity Regulatory Commission. For electrified areas up to 150 kW, they are fixed in advance by load and category so that no site inspection is needed to work them out (rule 4(13)).1

    Watch out

    • The time limit runs only from a complete application. If the discom says something is missing, ask it to say exactly what, in writing, and resubmit at once.
    • Keep the acknowledgement with the registration number. It fixes the date your time limit starts, and you can track the application with it (rules 4(7) and 4(8)).
  3. Pay the charges and wait for the connection

    Your discom

    Pay the charges the discom demands. It must then give the new connection, or make the change to your existing connection, within the time your State Commission sets. Since the 2024 amendment, the Rules cap this at 3 days in metropolitan areas, 7 days in other municipal areas, 15 days in rural areas and 30 days in rural areas of hilly terrain. If supply needs new distribution mains or a new substation, the connection is due as soon as that work is done, or within the time the Commission sets (rule 4(11), proviso).

    Time limit
    3 days in metropolitan areas, 7 days in other municipal areas, 15 days in rural areas, 30 days in rural hilly areas2Electricity (Rights of Consumers) Rules 2020, rule 4(11), as amended by the Electricity (Rights of Consumers) Amendment Rules 2024
    The message to send to your discom’s customer care, or the officer named on your acknowledgement

    Get a firm date before the time limit passes

    Fill in the message
    Dear Sir or Madam, I applied to Name of your discom for What you applied for, e.g. a new connection or a change of name at Address of the premises on Date of your complete application, registration number Registration number on the acknowledgement. Under rule 4(11) of the Electricity (Rights of Consumers) Rules 2020, it is due by Date the work is due. Please confirm the date the work will be done, or tell me in writing if anything is missing from my application. Thank you, Your name

    Watch out

    • The Rules do not define metropolitan, other municipal or rural areas. Ask the discom which category your premises fall in.
    • If the discom says new mains or a substation are needed, ask for the expected date in writing.
  4. Complain to the discom when the time limit passes

    Your discom’s 24x7 toll-free call centre, website or app

    If the time limit passes, register a complaint and note the complaint number. Every discom must run a centralised, 24x7 toll-free call centre (rule 14(1)) and give consumers SMS and email updates (rule 14(3)). Find the number on the discom’s website or app.

    The message to send to your discom’s call centre (by web complaint, app or email)

    Create a dated record of the delay

    Fill in the message
    Complaint: delay in What you applied for. Registration number Registration number, applied on Date of your complete application, premises Address of the premises. The work was due by Date the work was due under rule 4(11) of the Electricity (Rights of Consumers) Rules 2020 and has not been done. Please give me a complaint number and a date for the work, and confirm the compensation that will be credited under rule 13. Your name, Your phone number

    Watch out

    • Write down the complaint number, the date and time, and the name of anyone you speak to.
  5. Check that compensation is paid

    Your discom

    Your State Commission sets standards of performance and the compensation a discom must pay when it misses them (rule 12). The standards include the time taken for a connection, for a change of load or category, and for a change in consumer details (rule 13(4)). Where a standard can be monitored remotely, compensation is meant to be automatic (rule 13(1)); otherwise claim it through the discom’s online facility (rule 13(5)). It is paid by adjustment against your current or future bills (rule 13(6)).

    Watch out

    • Check your next bills for the credit. If it does not appear, include it in your complaint to the forum.
  6. Take the grievance to the Consumer Grievance Redressal Forum

    Consumer Grievance Redressal Forum (CGRF) of your discom45 days

    If the discom does not resolve your complaint, file a written grievance with its Consumer Grievance Redressal Forum. Every discom must set one up under section 42(5) of the Electricity Act 2003, with consumer representatives and an independent member nominated by the State Commission (rule 15(1)). The forum should normally decide within 30 days, and in any case within 45 days of receiving the grievance (rule 15(2)). If your discom has forums at several levels, you may go to the company-level forum before the Ombudsman.

    Time limit
    Decision normally within 30 days, and not more than 45 days, from receipt of the grievance1Electricity (Rights of Consumers) Rules 2020, rule 15(2)

    Watch out

    • The discom must publicise the forum’s office, address, contact details and how to register a grievance (rule 15(4)). Ask for these in writing if you cannot find them.
    • Your State Commission’s forum regulations may require you to complain to the discom first. Read them before filing.
  7. Appeal to the Electricity Ombudsman

    Electricity Ombudsman appointed by your State Electricity Regulatory Commission

    If the forum does not decide in time, or you are not satisfied with its decision, you can approach the Electricity Ombudsman appointed by the State Commission (rule 15(3)). The time limit for filing, the form and the procedure are set by your State Commission’s regulations.

    Watch out

    • Find your state’s time limit for approaching the Ombudsman as soon as the forum decides, and file well within it.

The legal clocks

6 deadlines

Each clock starts on a particular day. Enter that day to see your last day, and add it to your calendar. Counted the way the law counts by default: the start day is left out.

  • Acknowledgement of a paper application

    24 hours from when you hand in a complete paper application1

    If it runs out: Ask for the acknowledgement. The application counts as received on the date it is generated.

    Electricity (Rights of Consumers) Rules 2020, rule 4(7)

    Enter the date and the last day appears here.

  • Connection or change in a metropolitan area

    3 days from the date a complete application is acknowledged2

    If it runs out: The discom is in default. You are due compensation at the rate your State Commission sets (rules 12 and 13). Separately, the Commission can impose a penalty on the discom of up to ₹1,000 for each day of default (rule 4(12)).

    Electricity (Rights of Consumers) Rules 2020, rule 4(11) as amended in 2024; rules 4(12), 12 and 13

    Enter the date and the last day appears here.

  • Connection or change in another municipal area

    7 days from the date a complete application is acknowledged2

    If it runs out: The discom is in default. You are due compensation at the rate your State Commission sets (rules 12 and 13). Separately, the Commission can impose a penalty on the discom of up to ₹1,000 for each day of default (rule 4(12)).

    Electricity (Rights of Consumers) Rules 2020, rule 4(11) as amended in 2024; rules 4(12), 12 and 13

    Enter the date and the last day appears here.

  • Connection or change in a rural area

    15 days from the date a complete application is acknowledged2

    If it runs out: The discom is in default. You are due compensation at the rate your State Commission sets (rules 12 and 13). Separately, the Commission can impose a penalty on the discom of up to ₹1,000 for each day of default (rule 4(12)).

    Electricity (Rights of Consumers) Rules 2020, rule 4(11) as amended in 2024; rules 4(12), 12 and 13

    Enter the date and the last day appears here.

  • Connection or change in a rural area of hilly terrain

    30 days from the date a complete application is acknowledged2

    If it runs out: The discom is in default. You are due compensation at the rate your State Commission sets (rules 12 and 13). Separately, the Commission can impose a penalty on the discom of up to ₹1,000 for each day of default (rule 4(12)).

    Electricity (Rights of Consumers) Rules 2020, rule 4(11) as amended in 2024; rules 4(12), 12 and 13

    Enter the date and the last day appears here.

  • Forum decision

    45 days from the date the forum receives your grievance1

    If it runs out: If the forum has not decided, or you disagree with its decision, you may approach the Electricity Ombudsman.

    Electricity (Rights of Consumers) Rules 2020, rule 15(2) and (3)

    Enter the date and the last day appears here.

If the last day falls on a day the court or office is closed, the law usually lets you act on the next day it opens (General Clauses Act 1897, section 10). Working days here skip weekends only. When a day matters, confirm it with the office.

Letters

2 letters
  • Grievance to the Consumer Grievance Redressal ForumTo the Chairperson, Consumer Grievance Redressal Forum of your discom. When the discom has missed the time limit and has not resolved your complaint

    Electricity Act 2003, section 42(5); Electricity (Rights of Consumers) Rules 2020, rules 4(11), 12, 13 and 15

    Fill in the letter
    Date: Date of this letter To The Chairperson Consumer Grievance Redressal Forum Name of your discom Address of the forum Subject: Grievance about delay in What you applied for, e.g. a new connection, a change of name or a change of load, registration number Registration number of your application Dear Sir or Madam, 1. I applied to Name of your discom on Date of your complete application for What you applied for, e.g. a new connection, a change of name or a change of load at Address of the premises. My application was complete and was acknowledged with registration number Registration number of your application. 2. The premises are in a Metropolitan, other municipal, rural, or rural hilly area. Under rule 4(11) of the Electricity (Rights of Consumers) Rules 2020, as amended in 2024, and the State Commission’s standards of performance, the work was due by Date the work was due. It has not been done. 3. I complained to the discom on Date of your complaint to the discom (complaint number Complaint number given by the discom). The problem has not been resolved. 4. I ask the Forum to: (a) direct the discom to complete What you applied for, e.g. a new connection, a change of name or a change of load by a date the Forum fixes; (b) direct the discom to pay the compensation due under the State Commission’s standards of performance, as rules 12 and 13 require; and (c) decide this grievance within the time in rule 15(2), which is normally 30 days and not more than 45 days from receipt. Copies of my application, the acknowledgement, the payment receipt and my complaint are enclosed. Yours faithfully, Your full name Your postal address Phone: Your phone number Email: Your email address Enclosures: application, acknowledgement with registration number, payment receipt, complaint record

    Sending it: Use the forum’s online system if your discom has one, or send it by registered post with acknowledgement due, or hand it in against a stamped receipt. Keep the receipt or online reference number.

  • Representation to the Electricity OmbudsmanTo the Electricity Ombudsman appointed by your State Electricity Regulatory Commission. When the forum has not decided within 45 days, or you are not satisfied with its decision, within the time your state’s regulations allow

    Electricity (Rights of Consumers) Rules 2020, rule 15(3)

    Fill in the letter
    Date: Date of this letter To The Electricity Ombudsman, Your state Address of the Electricity Ombudsman Subject: Representation against Name of your discom about delay in What you applied for, forum grievance number Forum grievance number Dear Sir or Madam, 1. I applied to Name of your discom on Date of your complete application for What you applied for (registration number Registration number of your application). It was due by Date the work was due under rule 4(11) of the Electricity (Rights of Consumers) Rules 2020, as amended in 2024, and has not been done on time. 2. I filed a grievance with the Consumer Grievance Redressal Forum on Date you filed with the forum (number Forum grievance number). Outcome: What the forum did, e.g. no decision within 45 days, or its order dated on a stated date. 3. Rule 15(3) of the Rules allows a consumer to approach the Ombudsman appointed by the Commission when the forum has not redressed the grievance within the specified time or the consumer is not satisfied with its decision. 4. I ask the Ombudsman to: What you want the Ombudsman to order, and to direct payment of the compensation due under the State Commission’s standards of performance. Copies of my application, the acknowledgement, my complaint to the discom, the forum grievance and any forum order are enclosed. Yours faithfully, Your full name Your postal address Phone: Your phone number Email: Your email address

    Sending it: Send it by registered post with acknowledgement due, or file it in the form and manner your State Commission’s Ombudsman regulations require. Keep the proof of filing.

If nobody answers

3 levels
  1. Your discom’s 24x7 toll-free call centre, website or app

    As soon as the time limit for the connection or change passes1

    Register a complaint and note the complaint number

  2. Consumer Grievance Redressal Forum of your discom

    If the discom does not resolve your complaint1

    Written grievance (letter l1); the forum should decide normally within 30 days and not more than 45 days

  3. Electricity Ombudsman appointed by your State Electricity Regulatory Commission

    If the forum does not decide within 45 days, or you disagree with its decision1

    Written representation (letter l2) within the time set by your state’s regulations

By state

1 state
  • Maharashtra

    The Maharashtra Electricity Regulatory Commission’s explanatory memorandum for its 2024 First Amendment to the Supply Code regulations aligns the state with the 2024 Rules: 3 days in metropolitan areas, 7 days in other municipal areas and 15 days in rural areas where the existing network can supply, and 90 days where mains must be augmented or extended or a new substation commissioned. It sets compensation for a late connection at ₹50 for each week or part of a week of delay, up to twice the service connection charges for the consumer’s category, paid automatically.3 Official page

Questions people ask

6 questions
Can I get a connection as a tenant?
Yes. The Rules define an applicant as the owner or occupier of the premises, and an occupier includes a tenant (rule 2(1)(b) and (k)). You need identity proof and proof of ownership or occupancy, or another address proof if you have neither (rule 4(9)).
Which time limit applies to a change of name or load?
Rule 4(11) covers both new connections and changes to an existing connection, so the same caps apply to the work. Your State Commission must also set standards, with compensation, for the time taken to change the load or category and to change consumer details (rule 13(4)).
The discom says it must lay new lines first. Does the time limit still apply?
Where supply needs new distribution mains or a new substation, the discom must connect you as soon as that work is done, or within the time the State Commission sets (rule 4(11), proviso). Ask for the date in writing.
Our housing society has one bulk connection. Can residents get their own meters?
The 2024 amendment lets residents choose between individual connections and a single-point connection for the premises, through a transparent ballot run by the discom. It also allows a separate connection for charging an electric vehicle (Ministry of Power, 23 February 2024).
Is the ₹1,000 a day penalty paid to me?
No. Rule 4(12) lets the State Commission impose a penalty of up to ₹1,000 for each day of default on the discom. Compensation to you is separate and is set by the Commission’s standards of performance (rules 12 and 13).
Have the Rules changed again in 2026?
The Ministry of Power issued a draft Electricity (Rights of Consumers) Amendment Rules 2026 for comments on 12 March 2026. We found no final notification by 31 October 2026, so this guide follows the Rules as amended in 2024.

Sources

7 sources, checked 31 October 2026
  1. Electricity (Rights of Consumers) Rules, 2020 (Gazette notification of 31 December 2020)Ministry of Power, checked 31 October 2026
  2. Government amends Electricity (Rights of Consumers) Rules (press release on the Electricity (Rights of Consumers) Amendment Rules, 2024), 23 February 2024Press Information Bureau, Ministry of Power, checked 31 October 2026
  3. Explanatory Memorandum, MERC (Electricity Supply Code and Standards of Performance of Distribution Licensees including Power Quality) (First Amendment) Regulations, 2024 (May 2024)Maharashtra Electricity Regulatory Commission, checked 31 October 2026
  4. Rajya Sabha answers of 3 February 2025, including Unstarred Questions 153 and 156 (connection timelines including rural hilly areas)Ministry of Power, checked 31 October 2026
  5. Rajya Sabha Unstarred Question 950, answered 27 July 2026 (grievances handled under the 2020 Rules; multi-tier CGRFs and the Electricity Ombudsman)Ministry of Power, checked 31 October 2026
  6. MNRE Policy and Regulatory Updates, March 2026 (lists the Draft Electricity (Rights of Consumers) Amendment Rules, 2026 of 12 March 2026)Ministry of New and Renewable Energy, checked 31 October 2026
  7. Union Government lays down rights to electricity consumers through the Electricity (Rights of Consumers) Rules, 2020 (press release, 21 December 2020)Press Information Bureau, Ministry of Power, checked 31 October 2026

What we could not confirm

  • The 2024 amendment’s Gazette text could not be opened. Its timelines are taken from the Ministry of Power’s press release of 23 February 2024 (src2) and its Rajya Sabha answer of 3 February 2025 (src3). The G.S.R. number and exact Gazette date were not confirmed; secondary sources disagree.
  • Whether the 2024 amendment changed rule 4(9) on documents: the press release and secondary summaries mention no change, so the guide states the 2020 rule.
  • Draft Electricity (Rights of Consumers) Amendment Rules 2026 (12 March 2026): no final notification was found by 31 October 2026. Trade press reports say the draft would extend the 3-day limit to municipal corporation areas. If it is notified, the timelines change.
  • The Jan Vishwas (Amendment of Provisions) Act 2026 amended penalty provisions of the Electricity Act 2003 from 1 June 2026 (S.O. 2552(E), 18 May 2026). Secondary sources list sections 139 to 142, 146 and 152; the full schedule was not read, so it is not confirmed that section 43 (duty to supply, linked to the ₹1,000 a day penalty in rule 4(12)) is unchanged.
  • Electricity Act 2003, section 42(6) to (8) on the Ombudsman was not read (India Code blocks automated access); the guide relies on rule 15(3).
  • The common electricity complaint number 1912 was not confirmed from an official source, so no helpline is listed.
  • Ombudsman filing time limits, fees and procedures, and any requirement to complain to the discom first, were not checked for any state.
  • Maharashtra: the MERC explanatory memorandum (src5) carries ‘Draft’ page headers; the final notified First Amendment Regulations 2024 were not opened. Portals and forum details for MSEDCL, BEST, Adani Electricity Mumbai and Tata Power were not checked.
  • State notes not confirmed from official portals, to check: Delhi (BSES Rajdhani, BSES Yamuna, Tata Power-DDL and NDMC; Delhi Electricity Regulatory Commission; their forums and the Delhi Electricity Ombudsman); Karnataka (BESCOM, MESCOM, HESCOM, GESCOM and CESC Mysore; Karnataka Electricity Regulatory Commission and its Ombudsman); Tamil Nadu (the state’s distribution corporation; Tamil Nadu Electricity Regulatory Commission and its Ombudsman); Uttar Pradesh (UPPCL’s distribution companies and Noida Power Company; Uttar Pradesh Electricity Regulatory Commission and its Ombudsman); West Bengal (WBSEDCL and CESC Limited; West Bengal Electricity Regulatory Commission and its Ombudsman). Portals, forum addresses, timelines and compensation amounts for these states were not checked.
  • The meaning of metropolitan, other municipal and rural areas: the Rules do not define them, and state regulations were not checked.

This guide sets out the law and the official procedure as published, with every source linked. It is not legal advice for your case. Rules change: if something here is wrong or out of date, write to us and the page is corrected and re-dated. Free to reuse with credit under CC BY 4.0. The whole guide is also published as data for apps and agents.

Kitaab can carry this for you.

Tell Kitaab what you’re waiting on. It drafts each message in the other person’s language for your approval, keeps every reply with what you asked, and reminds you before each deadline.