 "url": "https://kitaab.live/guides/electricity-connection",
 "licence": {
  "name": "CC BY 4.0",
  "url": "https://creativecommons.org/licenses/by/4.0/"
 },
 "publisher": {
  "name": "Kitaab (Opankitaab Private Limited)",
  "url": "https://kitaab.live",
  "email": "hello@kitaab.live"
 },
 "country": "IN",
 "language": "en-IN",
 "slug": "electricity-connection",
 "title": "Get a new electricity connection, or change the name or load",
 "ask": "I need a new electricity connection, or a change of name or load on my existing one. How do I apply, how long can the discom take, and what if it is late?",
 "summary": "Your electricity distribution company (discom) must connect you, or change your connection, within fixed times once your application is complete: at most 3 days in metropolitan areas, 7 days in other municipal areas, 15 days in rural areas and 30 days in rural hilly areas. These caps come from the Electricity (Rights of Consumers) Rules 2020 as amended in 2024. The clock starts only when your application is complete and acknowledged, so keep the registration number.",
 "area": "home",
 "jurisdiction": {
  "scope": "state-varies",
  "note": "The Electricity (Rights of Consumers) Rules 2020 set national rights and maximum timelines; each State Electricity Regulatory Commission sets the exact timelines, charges, compensation amounts and grievance procedures for its discoms."
 },
 "applies_when": [
  "You need a new electricity connection for a home or other premises",
  "You want to change the name on an existing connection, for example after buying the home or after the account holder’s death",
  "You want to increase or reduce the sanctioned load, or change the category",
  "Your discom has not connected you, or made the change, within the time limit"
 ],
 "not_for": [
  {
   "text": "Disputing a high or wrong electricity bill",
   "slug": null
  },
  {
   "text": "Rooftop solar and net metering applications",
   "slug": null
  },
  {
   "text": "Assessments for theft or unauthorised use of electricity",
   "slug": null
  }
 ],
 "before_you_start": [
  "Find out which discom serves the premises, for example from a neighbour’s bill.",
  "Decide the load you need in kW and the category, such as domestic or commercial.",
  "Ask whether the premises are in a metropolitan, other municipal or rural area. This decides your time limit.",
  "If you rent, use proof of occupancy such as your rent agreement; the Rules also allow another address proof if you have no ownership or occupancy proof.",
  "For a change of name, check your discom’s published list of documents for changes."
 ],
 "documents": [
  {
   "id": "id-proof",
   "name": "Identity proof of the applicant",
   "note": "For example a passport or Aadhaar card, as rule 4(9) gives as examples.",
   "required": true
  },
  {
   "id": "occupancy-proof",
   "name": "Proof of ownership or occupancy of the premises",
   "note": "If you have neither, rule 4(9) allows any other address proof that you have not already given as identity proof.",
   "required": true
  },
  {
   "id": "load-details",
   "name": "The load in kW and the category you need",
   "note": "For example domestic or commercial. The discom’s form asks for these.",
   "required": true
  },
  {
   "id": "consumer-number",
   "name": "Existing consumer or account number",
   "note": "Only for a change of name, load or category on an existing connection.",
   "required": false
  },
  {
   "id": "change-proof",
   "name": "Proof supporting a change of name",
   "note": "Your State Commission specifies the documents for changes to an existing connection, and your discom must publish the list.",
   "required": false
  }
 ],
 "steps": [
  {
   "id": "s1",
   "title": "Find your discom’s procedure and charges",
   "who": {
    "kind": "company",
    "name": "Your electricity distribution company (discom)"
   },
   "what": "Every discom must publish its procedure, the documents it needs and its charges on its website and on the notice board of its offices (rule 4(1)). Application forms must be free, and every discom must run a web portal and a mobile app for applications (rules 4(2) and 4(3)). Find the ‘new connection’ or ‘change of name’ service on your discom’s website or app.",
   "documents": [],
   "fee": {
    "text": "Application form: free",
    "source": "src1"
   },
   "time_limit": null,
   "typical_time": null,
   "online": null,
   "depends_on": [],
   "message": null,
   "watch_out": [
    "Check any amount you are asked to pay against the discom’s published charges."
   ]
  },
  {
   "id": "s2",
   "title": "Apply and get a registration number",
   "who": {
    "kind": "company",
    "name": "Your discom’s portal, app or local office"
   },
   "what": "Apply online or at the office. For connections up to 10 kW, or a higher load if your State Commission allows, the discom may ask for only two documents: identity proof, and proof of ownership or occupancy of the premises (rule 4(9)). A complete application counts as received on the date the acknowledgement with a registration number is generated; for a paper application, that must happen within a time the Commission sets, not more than 24 hours (rule 4(7)). For a change of name or load, apply the same way; your State Commission sets the documents for changes.",
   "documents": [
    "id-proof",
    "occupancy-proof",
    "load-details",
    "consumer-number",
    "change-proof"
   ],
   "fee": {
    "text": "Connection charges are set by your State Electricity Regulatory Commission. For electrified areas up to 150 kW, they are fixed in advance by load and category so that no site inspection is needed to work them out (rule 4(13)).",
    "source": "src1"
   },
   "time_limit": {
    "text": "Acknowledgement of a paper application within the time the Commission sets, not more than 24 hours",
    "days": null,
    "from": "the time you hand in a complete paper application",
    "basis": "Electricity (Rights of Consumers) Rules 2020, rule 4(7)",
    "source": "src1"
   },
   "typical_time": null,
   "online": null,
   "depends_on": [
    "s1"
   ],
   "message": null,
   "watch_out": [
    "The time limit runs only from a complete application. If the discom says something is missing, ask it to say exactly what, in writing, and resubmit at once.",
    "Keep the acknowledgement with the registration number. It fixes the date your time limit starts, and you can track the application with it (rules 4(7) and 4(8))."
   ]
  },
  {
   "id": "s3",
   "title": "Pay the charges and wait for the connection",
   "who": {
    "kind": "company",
    "name": "Your discom"
   },
   "what": "Pay the charges the discom demands. It must then give the new connection, or make the change to your existing connection, within the time your State Commission sets. Since the 2024 amendment, the Rules cap this at 3 days in metropolitan areas, 7 days in other municipal areas, 15 days in rural areas and 30 days in rural areas of hilly terrain. If supply needs new distribution mains or a new substation, the connection is due as soon as that work is done, or within the time the Commission sets (rule 4(11), proviso).",
   "documents": [],
   "fee": null,
   "time_limit": {
    "text": "3 days in metropolitan areas, 7 days in other municipal areas, 15 days in rural areas, 30 days in rural hilly areas",
    "days": null,
    "from": "the date a complete application is acknowledged",
    "basis": "Electricity (Rights of Consumers) Rules 2020, rule 4(11), as amended by the Electricity (Rights of Consumers) Amendment Rules 2024",
    "source": "src2"
   },
   "typical_time": null,
   "online": null,
   "depends_on": [
    "s2"
   ],
   "message": {
    "to": "Your discom’s customer care, or the officer named on your acknowledgement",
    "purpose": "Get a firm date before the time limit passes",
    "fields": [
     {
      "key": "discom_name",
      "label": "Name of your discom"
     },
     {
      "key": "request_type",
      "label": "What you applied for, e.g. a new connection or a change of name"
     },
     {
      "key": "premises_address",
      "label": "Address of the premises"
     },
     {
      "key": "application_date",
      "label": "Date of your complete application"
     },
     {
      "key": "registration_number",
      "label": "Registration number on the acknowledgement"
     },
     {
      "key": "deadline_date",
      "label": "Date the work is due"
     },
     {
      "key": "your_name",
      "label": "Your name"
     }
    ],
    "text": "Dear Sir or Madam, I applied to {discom_name} for {request_type} at {premises_address} on {application_date}, registration number {registration_number}. Under rule 4(11) of the Electricity (Rights of Consumers) Rules 2020, it is due by {deadline_date}. Please confirm the date the work will be done, or tell me in writing if anything is missing from my application. Thank you, {your_name}"
   },
   "watch_out": [
    "The Rules do not define metropolitan, other municipal or rural areas. Ask the discom which category your premises fall in.",
    "If the discom says new mains or a substation are needed, ask for the expected date in writing."
   ]
  },
  {
   "id": "s4",
   "title": "Complain to the discom when the time limit passes",
   "who": {
    "kind": "company",
    "name": "Your discom’s 24x7 toll-free call centre, website or app"
   },
   "what": "If the time limit passes, register a complaint and note the complaint number. Every discom must run a centralised, 24x7 toll-free call centre (rule 14(1)) and give consumers SMS and email updates (rule 14(3)). Find the number on the discom’s website or app.",
   "documents": [],
   "fee": null,
   "time_limit": null,
   "typical_time": null,
   "online": null,
   "depends_on": [
    "s3"
   ],
   "message": {
    "to": "Your discom’s call centre (by web complaint, app or email)",
    "purpose": "Create a dated record of the delay",
    "fields": [
     {
      "key": "request_type",
      "label": "What you applied for"
     },
     {
      "key": "registration_number",
      "label": "Registration number"
     },
     {
      "key": "application_date",
      "label": "Date of your complete application"
     },
     {
      "key": "premises_address",
      "label": "Address of the premises"
     },
     {
      "key": "deadline_date",
      "label": "Date the work was due"
     },
     {
      "key": "your_name",
      "label": "Your name"
     },
     {
      "key": "your_phone",
      "label": "Your phone number"
     }
    ],
    "text": "Complaint: delay in {request_type}. Registration number {registration_number}, applied on {application_date}, premises {premises_address}. The work was due by {deadline_date} under rule 4(11) of the Electricity (Rights of Consumers) Rules 2020 and has not been done. Please give me a complaint number and a date for the work, and confirm the compensation that will be credited under rule 13. {your_name}, {your_phone}"
   },
   "watch_out": [
    "Write down the complaint number, the date and time, and the name of anyone you speak to."
   ]
  },
  {
   "id": "s5",
   "title": "Check that compensation is paid",
   "who": {
    "kind": "company",
    "name": "Your discom"
   },
   "what": "Your State Commission sets standards of performance and the compensation a discom must pay when it misses them (rule 12). The standards include the time taken for a connection, for a change of load or category, and for a change in consumer details (rule 13(4)). Where a standard can be monitored remotely, compensation is meant to be automatic (rule 13(1)); otherwise claim it through the discom’s online facility (rule 13(5)). It is paid by adjustment against your current or future bills (rule 13(6)).",
   "documents": [],
   "fee": null,
   "time_limit": null,
   "typical_time": null,
   "online": null,
   "depends_on": [
    "s4"
   ],
   "message": null,
   "watch_out": [
    "Check your next bills for the credit. If it does not appear, include it in your complaint to the forum."
   ]
  },
  {
   "id": "s6",
   "title": "Take the grievance to the Consumer Grievance Redressal Forum",
   "who": {
    "kind": "office",
    "name": "Consumer Grievance Redressal Forum (CGRF) of your discom"
   },
   "what": "If the discom does not resolve your complaint, file a written grievance with its Consumer Grievance Redressal Forum. Every discom must set one up under section 42(5) of the Electricity Act 2003, with consumer representatives and an independent member nominated by the State Commission (rule 15(1)). The forum should normally decide within 30 days, and in any case within 45 days of receiving the grievance (rule 15(2)). If your discom has forums at several levels, you may go to the company-level forum before the Ombudsman.",
   "documents": [],
   "fee": null,
   "time_limit": {
    "text": "Decision normally within 30 days, and not more than 45 days, from receipt of the grievance",
    "days": 45,
    "from": "the date the forum receives your grievance",
    "basis": "Electricity (Rights of Consumers) Rules 2020, rule 15(2)",
    "source": "src1"
   },
   "typical_time": null,
   "online": null,
   "depends_on": [
    "s4"
   ],
   "message": null,
   "watch_out": [
    "The discom must publicise the forum’s office, address, contact details and how to register a grievance (rule 15(4)). Ask for these in writing if you cannot find them.",
    "Your State Commission’s forum regulations may require you to complain to the discom first. Read them before filing."
   ]
  },
  {
   "id": "s7",
   "title": "Appeal to the Electricity Ombudsman",
   "who": {
    "kind": "office",
    "name": "Electricity Ombudsman appointed by your State Electricity Regulatory Commission"
   },
   "what": "If the forum does not decide in time, or you are not satisfied with its decision, you can approach the Electricity Ombudsman appointed by the State Commission (rule 15(3)). The time limit for filing, the form and the procedure are set by your State Commission’s regulations.",
   "documents": [],
   "fee": null,
   "time_limit": null,
   "typical_time": null,
   "online": null,
   "depends_on": [
    "s6"
   ],
   "message": null,
   "watch_out": [
    "Find your state’s time limit for approaching the Ombudsman as soon as the forum decides, and file well within it."
   ]
  }
 ],
 "clocks": [
  {
   "id": "c1",
   "name": "Acknowledgement of a paper application",
   "starts": "when you hand in a complete paper application",
   "duration": {
    "value": 24,
    "unit": "hours"
   },
   "then": "Ask for the acknowledgement. The application counts as received on the date it is generated.",
   "basis": "Electricity (Rights of Consumers) Rules 2020, rule 4(7)",
   "source": "src1"
  },
  {
   "id": "c2",
   "name": "Connection or change in a metropolitan area",
   "starts": "the date a complete application is acknowledged",
   "duration": {
    "value": 3,
    "unit": "days"
   },
   "then": "The discom is in default. You are due compensation at the rate your State Commission sets (rules 12 and 13). Separately, the Commission can impose a penalty on the discom of up to ₹1,000 for each day of default (rule 4(12)).",
   "basis": "Electricity (Rights of Consumers) Rules 2020, rule 4(11) as amended in 2024; rules 4(12), 12 and 13",
   "source": "src2"
  },
  {
   "id": "c3",
   "name": "Connection or change in another municipal area",
   "starts": "the date a complete application is acknowledged",
   "duration": {
    "value": 7,
    "unit": "days"
   },
   "then": "The discom is in default. You are due compensation at the rate your State Commission sets (rules 12 and 13). Separately, the Commission can impose a penalty on the discom of up to ₹1,000 for each day of default (rule 4(12)).",
   "basis": "Electricity (Rights of Consumers) Rules 2020, rule 4(11) as amended in 2024; rules 4(12), 12 and 13",
   "source": "src2"
  },
  {
   "id": "c4",
   "name": "Connection or change in a rural area",
   "starts": "the date a complete application is acknowledged",
   "duration": {
    "value": 15,
    "unit": "days"
   },
   "then": "The discom is in default. You are due compensation at the rate your State Commission sets (rules 12 and 13). Separately, the Commission can impose a penalty on the discom of up to ₹1,000 for each day of default (rule 4(12)).",
   "basis": "Electricity (Rights of Consumers) Rules 2020, rule 4(11) as amended in 2024; rules 4(12), 12 and 13",
   "source": "src2"
  },
  {
   "id": "c5",
   "name": "Connection or change in a rural area of hilly terrain",
   "starts": "the date a complete application is acknowledged",
   "duration": {
    "value": 30,
    "unit": "days"
   },
   "then": "The discom is in default. You are due compensation at the rate your State Commission sets (rules 12 and 13). Separately, the Commission can impose a penalty on the discom of up to ₹1,000 for each day of default (rule 4(12)).",
   "basis": "Electricity (Rights of Consumers) Rules 2020, rule 4(11) as amended in 2024; rules 4(12), 12 and 13",
   "source": "src2"
  },
  {
   "id": "c6",
   "name": "Forum decision",
   "starts": "the date the forum receives your grievance",
   "duration": {
    "value": 45,
    "unit": "days"
   },
   "then": "If the forum has not decided, or you disagree with its decision, you may approach the Electricity Ombudsman.",
   "basis": "Electricity (Rights of Consumers) Rules 2020, rule 15(2) and (3)",
   "source": "src1"
  }
 ],
 "letters": [
  {
   "id": "l1",
   "title": "Grievance to the Consumer Grievance Redressal Forum",
   "to": "The Chairperson, Consumer Grievance Redressal Forum of your discom",
   "when": "When the discom has missed the time limit and has not resolved your complaint",
   "basis": "Electricity Act 2003, section 42(5); Electricity (Rights of Consumers) Rules 2020, rules 4(11), 12, 13 and 15",
   "fields": [
    {
     "key": "letter_date",
     "label": "Date of this letter"
    },
    {
     "key": "discom_name",
     "label": "Name of your discom"
    },
    {
     "key": "forum_address",
     "label": "Address of the forum"
    },
    {
     "key": "request_type",
     "label": "What you applied for, e.g. a new connection, a change of name or a change of load"
    },
    {
     "key": "registration_number",
     "label": "Registration number of your application"
    },
    {
     "key": "application_date",
     "label": "Date of your complete application"
    },
    {
     "key": "premises_address",
     "label": "Address of the premises"
    },
    {
     "key": "area_type",
     "label": "Metropolitan, other municipal, rural, or rural hilly"
    },
    {
     "key": "deadline_date",
     "label": "Date the work was due"
    },
    {
     "key": "complaint_date",
     "label": "Date of your complaint to the discom"
    },
    {
     "key": "complaint_number",
     "label": "Complaint number given by the discom"
    },
    {
     "key": "your_name",
     "label": "Your full name"
    },
    {
     "key": "your_address",
     "label": "Your postal address"
    },
    {
     "key": "your_phone",
     "label": "Your phone number"
    },
    {
     "key": "your_email",
     "label": "Your email address"
    }
   ],
   "body": "Date: {letter_date}\n\nTo\nThe Chairperson\nConsumer Grievance Redressal Forum\n{discom_name}\n{forum_address}\n\nSubject: Grievance about delay in {request_type}, registration number {registration_number}\n\nDear Sir or Madam,\n\n1. I applied to {discom_name} on {application_date} for {request_type} at {premises_address}. My application was complete and was acknowledged with registration number {registration_number}.\n\n2. The premises are in a {area_type} area. Under rule 4(11) of the Electricity (Rights of Consumers) Rules 2020, as amended in 2024, and the State Commission’s standards of performance, the work was due by {deadline_date}. It has not been done.\n\n3. I complained to the discom on {complaint_date} (complaint number {complaint_number}). The problem has not been resolved.\n\n4. I ask the Forum to:\n(a) direct the discom to complete {request_type} by a date the Forum fixes;\n(b) direct the discom to pay the compensation due under the State Commission’s standards of performance, as rules 12 and 13 require; and\n(c) decide this grievance within the time in rule 15(2), which is normally 30 days and not more than 45 days from receipt.\n\nCopies of my application, the acknowledgement, the payment receipt and my complaint are enclosed.\n\nYours faithfully,\n\n{your_name}\n{your_address}\nPhone: {your_phone}\nEmail: {your_email}\n\nEnclosures: application, acknowledgement with registration number, payment receipt, complaint record",
   "send": "Use the forum’s online system if your discom has one, or send it by registered post with acknowledgement due, or hand it in against a stamped receipt. Keep the receipt or online reference number."
  },
  {
   "id": "l2",
   "title": "Representation to the Electricity Ombudsman",
   "to": "The Electricity Ombudsman appointed by your State Electricity Regulatory Commission",
   "when": "When the forum has not decided within 45 days, or you are not satisfied with its decision, within the time your state’s regulations allow",
   "basis": "Electricity (Rights of Consumers) Rules 2020, rule 15(3)",
   "fields": [
    {
     "key": "letter_date",
     "label": "Date of this letter"
    },
    {
     "key": "state_name",
     "label": "Your state"
    },
    {
     "key": "ombudsman_address",
     "label": "Address of the Electricity Ombudsman"
    },
    {
     "key": "discom_name",
     "label": "Name of your discom"
    },
    {
     "key": "request_type",
     "label": "What you applied for"
    },
    {
     "key": "registration_number",
     "label": "Registration number of your application"
    },
    {
     "key": "application_date",
     "label": "Date of your complete application"
    },
    {
     "key": "deadline_date",
     "label": "Date the work was due"
    },
    {
     "key": "grievance_number",
     "label": "Forum grievance number"
    },
    {
     "key": "grievance_date",
     "label": "Date you filed with the forum"
    },
    {
     "key": "forum_outcome",
     "label": "What the forum did, e.g. no decision within 45 days, or its order dated on a stated date"
    },
    {
     "key": "relief_sought",
     "label": "What you want the Ombudsman to order"
    },
    {
     "key": "your_name",
     "label": "Your full name"
    },
    {
     "key": "your_address",
     "label": "Your postal address"
    },
    {
     "key": "your_phone",
     "label": "Your phone number"
    },
    {
     "key": "your_email",
     "label": "Your email address"
    }
   ],
   "body": "Date: {letter_date}\n\nTo\nThe Electricity Ombudsman, {state_name}\n{ombudsman_address}\n\nSubject: Representation against {discom_name} about delay in {request_type}, forum grievance number {grievance_number}\n\nDear Sir or Madam,\n\n1. I applied to {discom_name} on {application_date} for {request_type} (registration number {registration_number}). It was due by {deadline_date} under rule 4(11) of the Electricity (Rights of Consumers) Rules 2020, as amended in 2024, and has not been done on time.\n\n2. I filed a grievance with the Consumer Grievance Redressal Forum on {grievance_date} (number {grievance_number}). Outcome: {forum_outcome}.\n\n3. Rule 15(3) of the Rules allows a consumer to approach the Ombudsman appointed by the Commission when the forum has not redressed the grievance within the specified time or the consumer is not satisfied with its decision.\n\n4. I ask the Ombudsman to: {relief_sought}, and to direct payment of the compensation due under the State Commission’s standards of performance.\n\nCopies of my application, the acknowledgement, my complaint to the discom, the forum grievance and any forum order are enclosed.\n\nYours faithfully,\n\n{your_name}\n{your_address}\nPhone: {your_phone}\nEmail: {your_email}",
   "send": "Send it by registered post with acknowledgement due, or file it in the form and manner your State Commission’s Ombudsman regulations require. Keep the proof of filing."
  }
 ],
 "escalation": [
  {
   "level": 1,
   "to": "Your discom’s 24x7 toll-free call centre, website or app",
   "when": "As soon as the time limit for the connection or change passes",
   "how": "Register a complaint and note the complaint number",
   "url": null,
   "source": "src1"
  },
  {
   "level": 2,
   "to": "Consumer Grievance Redressal Forum of your discom",
   "when": "If the discom does not resolve your complaint",
   "how": "Written grievance (letter l1); the forum should decide normally within 30 days and not more than 45 days",
   "url": null,
   "source": "src1"
  },
  {
   "level": 3,
   "to": "Electricity Ombudsman appointed by your State Electricity Regulatory Commission",
   "when": "If the forum does not decide within 45 days, or you disagree with its decision",
   "how": "Written representation (letter l2) within the time set by your state’s regulations",
   "url": null,
   "source": "src1"
  }
 ],
 "helplines": [],
 "state_notes": [
  {
   "state": "Maharashtra",
   "items": [
    {
     "note": "The Maharashtra Electricity Regulatory Commission’s explanatory memorandum for its 2024 First Amendment to the Supply Code regulations aligns the state with the 2024 Rules: 3 days in metropolitan areas, 7 days in other municipal areas and 15 days in rural areas where the existing network can supply, and 90 days where mains must be augmented or extended or a new substation commissioned. It sets compensation for a late connection at ₹50 for each week or part of a week of delay, up to twice the service connection charges for the consumer’s category, paid automatically.",
     "url": "https://merc.gov.in/wp-content/uploads/2024/05/EM-1st-Amendment-Supply-Code-Regulations-2024.pdf",
     "source": "src5"
    }
   ]
  }
 ],
 "faqs": [
  {
   "q": "Can I get a connection as a tenant?",
   "a": "Yes. The Rules define an applicant as the owner or occupier of the premises, and an occupier includes a tenant (rule 2(1)(b) and (k)). You need identity proof and proof of ownership or occupancy, or another address proof if you have neither (rule 4(9))."
  },
  {
   "q": "Which time limit applies to a change of name or load?",
   "a": "Rule 4(11) covers both new connections and changes to an existing connection, so the same caps apply to the work. Your State Commission must also set standards, with compensation, for the time taken to change the load or category and to change consumer details (rule 13(4))."
  },
  {
   "q": "The discom says it must lay new lines first. Does the time limit still apply?",
   "a": "Where supply needs new distribution mains or a new substation, the discom must connect you as soon as that work is done, or within the time the State Commission sets (rule 4(11), proviso). Ask for the date in writing."
  },
  {
   "q": "Our housing society has one bulk connection. Can residents get their own meters?",
   "a": "The 2024 amendment lets residents choose between individual connections and a single-point connection for the premises, through a transparent ballot run by the discom. It also allows a separate connection for charging an electric vehicle (Ministry of Power, 23 February 2024)."
  },
  {
   "q": "Is the ₹1,000 a day penalty paid to me?",
   "a": "No. Rule 4(12) lets the State Commission impose a penalty of up to ₹1,000 for each day of default on the discom. Compensation to you is separate and is set by the Commission’s standards of performance (rules 12 and 13)."
  },
  {
   "q": "Have the Rules changed again in 2026?",
   "a": "The Ministry of Power issued a draft Electricity (Rights of Consumers) Amendment Rules 2026 for comments on 12 March 2026. We found no final notification by 31 October 2026, so this guide follows the Rules as amended in 2024."
  }
 ],
 "sources": [
  {
   "id": "src1",
   "title": "Electricity (Rights of Consumers) Rules, 2020 (Gazette notification of 31 December 2020)",
   "publisher": "Ministry of Power",
   "url": "https://powermin.gov.in/sites/default/files/uploads/Consumers_Rules_2020.pdf",
   "type": "rules",
   "checked": "2026-10-31",
   "n": 1
  },
  {
   "id": "src2",
   "title": "Government amends Electricity (Rights of Consumers) Rules (press release on the Electricity (Rights of Consumers) Amendment Rules, 2024), 23 February 2024",
   "publisher": "Press Information Bureau, Ministry of Power",
   "url": "https://www.pib.gov.in/PressReleaseIframePage.aspx?PRID=2008289",
   "type": "official-portal",
   "checked": "2026-10-31",
   "n": 2
  },
  {
   "id": "src5",
   "title": "Explanatory Memorandum, MERC (Electricity Supply Code and Standards of Performance of Distribution Licensees including Power Quality) (First Amendment) Regulations, 2024 (May 2024)",
   "publisher": "Maharashtra Electricity Regulatory Commission",
   "url": "https://merc.gov.in/wp-content/uploads/2024/05/EM-1st-Amendment-Supply-Code-Regulations-2024.pdf",
   "type": "rules",
   "checked": "2026-10-31",
   "n": 3
  },
  {
   "id": "src3",
   "title": "Rajya Sabha answers of 3 February 2025, including Unstarred Questions 153 and 156 (connection timelines including rural hilly areas)",
   "publisher": "Ministry of Power",
   "url": "https://www.powermin.gov.in/static/uploads/2025/08/5804f7f17e764f9ba1951183379b8e31.pdf",
   "type": "official-portal",
   "checked": "2026-10-31",
   "n": 4
  },
  {
   "id": "src4",
   "title": "Rajya Sabha Unstarred Question 950, answered 27 July 2026 (grievances handled under the 2020 Rules; multi-tier CGRFs and the Electricity Ombudsman)",
   "publisher": "Ministry of Power",
   "url": "https://www.powermin.gov.in/static/uploads/2026/07/f59419a881df9acc24bed8753f6d9fda.pdf",
   "type": "official-portal",
   "checked": "2026-10-31",
   "n": 5
  },
  {
   "id": "src6",
   "title": "MNRE Policy and Regulatory Updates, March 2026 (lists the Draft Electricity (Rights of Consumers) Amendment Rules, 2026 of 12 March 2026)",
   "publisher": "Ministry of New and Renewable Energy",
   "url": "https://cdnbbsr.s3waas.gov.in/s3716e1b8c6cd17b771da77391355749f3/uploads/2026/04/20260409820674347.pdf",
   "type": "official-portal",
   "checked": "2026-10-31",
   "n": 6
  },
  {
   "id": "src7",
   "title": "Union Government lays down rights to electricity consumers through the Electricity (Rights of Consumers) Rules, 2020 (press release, 21 December 2020)",
   "publisher": "Press Information Bureau, Ministry of Power",
   "url": "https://www.pib.gov.in/PressReleasePage.aspx?PRID=1682384&reg=48&lang=2",
   "type": "official-portal",
   "checked": "2026-10-31",
   "n": 7
  }
 ],
 "confidence": {
  "level": "medium",
  "unverified": [
   "The 2024 amendment’s Gazette text could not be opened. Its timelines are taken from the Ministry of Power’s press release of 23 February 2024 (src2) and its Rajya Sabha answer of 3 February 2025 (src3). The G.S.R. number and exact Gazette date were not confirmed; secondary sources disagree.",
   "Whether the 2024 amendment changed rule 4(9) on documents: the press release and secondary summaries mention no change, so the guide states the 2020 rule.",
   "Draft Electricity (Rights of Consumers) Amendment Rules 2026 (12 March 2026): no final notification was found by 31 October 2026. Trade press reports say the draft would extend the 3-day limit to municipal corporation areas. If it is notified, the timelines change.",
   "The Jan Vishwas (Amendment of Provisions) Act 2026 amended penalty provisions of the Electricity Act 2003 from 1 June 2026 (S.O. 2552(E), 18 May 2026). Secondary sources list sections 139 to 142, 146 and 152; the full schedule was not read, so it is not confirmed that section 43 (duty to supply, linked to the ₹1,000 a day penalty in rule 4(12)) is unchanged.",
   "Electricity Act 2003, section 42(6) to (8) on the Ombudsman was not read (India Code blocks automated access); the guide relies on rule 15(3).",
   "The common electricity complaint number 1912 was not confirmed from an official source, so no helpline is listed.",
   "Ombudsman filing time limits, fees and procedures, and any requirement to complain to the discom first, were not checked for any state.",
   "Maharashtra: the MERC explanatory memorandum (src5) carries ‘Draft’ page headers; the final notified First Amendment Regulations 2024 were not opened. Portals and forum details for MSEDCL, BEST, Adani Electricity Mumbai and Tata Power were not checked.",
   "State notes not confirmed from official portals, to check: Delhi (BSES Rajdhani, BSES Yamuna, Tata Power-DDL and NDMC; Delhi Electricity Regulatory Commission; their forums and the Delhi Electricity Ombudsman); Karnataka (BESCOM, MESCOM, HESCOM, GESCOM and CESC Mysore; Karnataka Electricity Regulatory Commission and its Ombudsman); Tamil Nadu (the state’s distribution corporation; Tamil Nadu Electricity Regulatory Commission and its Ombudsman); Uttar Pradesh (UPPCL’s distribution companies and Noida Power Company; Uttar Pradesh Electricity Regulatory Commission and its Ombudsman); West Bengal (WBSEDCL and CESC Limited; West Bengal Electricity Regulatory Commission and its Ombudsman). Portals, forum addresses, timelines and compensation amounts for these states were not checked.",
   "The meaning of metropolitan, other municipal and rural areas: the Rules do not define them, and state regulations were not checked."
  ]
 },
 "last_checked": "2026-10-31"
}